    Lake Arapakis commented  · 

    You can make the shift of the whole program via the little horizontal bars on any of the days. I have copied the following from another blog post by Gale Berhardt. You can see that post at: http://galebernhardt.com/blogs/news/16950684-how-can-i-easily-move-your-70-3-triathlon-training-plan-forward-one-day.

    "Assuming you do want to make the move, TrainingPeaks premier has a great feature that allows a good deal of flexibility. Notice that there are tiny lines on the upper right side each day in the calendar view. If you select those lines, a pop-up box appears and one option is "shift." Select this option.

    The shift option allows you to move:
    - items on selected days
    - items within a specified date range
    - items on and after a specified start date

    It asks how you want to shift the items:
    - move to a new start date
    - move by a specified number of days
    - move by a specified number of weeks

    I think this will get you what you need.